3
votes
2answers
265 views

How to notate that a task can't be started until a separate task is completed in GTD

I did a search through the site and found some similar questions with some answers that aren't quite what I'm after. What I'm looking for is if there is a recommended way to note that a task is ...
9
votes
6answers
977 views

Todo list manager that lets you queue next actions out of sight

I'm currently using Remember The Milk for my organisation system that is based on GTD. One thing that I find is missing from my system is the ability to capture all the actions relating to a project. ...
8
votes
2answers
1k views

Is there a way to link tasks in Remember the Milk?

I'm looking for a way to create a context list in Remember the Milk such that only next actions show up, but when I complete a task its successor task automatically shows up in the list. Is there a ...
3
votes
4answers
293 views

Handling delayed delegating in GTD

In GTD, how do you handle delegating an action if the act of delegating itself cannot be accomplished right when you are processing your inbox, and in less than two minutes? e.g. "summarize the last ...
6
votes
3answers
839 views

Handling task dependencies with GTD

How does Getting Things Done (GTD) recommend handling task dependencies (one task that can't be started until another task is completed)? I understand how it works when they are part of the same ...